On March 3, the Chongtai Yangtze River Tunnel 35 kV power supply supporting project was successfully put into operation, including key equipment such as switch cabinets, isolating switches, vacuum circuit breakers, lightning arresters and drop-out fuses, etc., which is a key project in the next stage of the project. Node - the formal excavation of the world's largest diameter high-speed rail mud-water balance shield machine "Pilot" provides a strong impetus.
It is understood that the "Pilot" shield machine used for this tunnel excavation has a cutter head diameter of 15.4 meters, a main engine length of about 15.8 meters, a total length of about 128 meters, and a main engine weight of about 2,600 tons. It is the longest single-head excavation distance in the world ( 11.325 kilometers) and the largest diameter (15.4 meters) shield engineering machinery. After completing assembly and commissioning, the "Pilot" will start from the No. 3 shaft in Wan'an Village, Miao Town, Chongming, and tunnel 11,325.5 meters across the Yangtze River to reach the No. 2 shaft in Taicang City, Jiangsu Province, connecting Chongming, Shanghai and Taicang, Jiangsu Province.
The shield machine needs to excavate continuously 24 hours a day, and reliable uninterrupted power supply has become the key to its power supply. The power supply system ensures the reliability and safety of power supply through carefully configured switch cabinets and isolation switches. At the same time, the vacuum circuit breaker can quickly cut off the circuit when necessary to avoid the expansion of the fault. Surge arresters and drop-out fuses effectively protect the power supply system from damage by lightning and overload current.
The power supply supporting project of the project will be implemented on January 4, 2024. The project's new civil construction length of pipes is 988 meters, 35 kV overhead lines are 7.63 kilometers, and cables (double-split) are 1.2 kilometers. At the same time, the project also includes the installation and debugging of transformers to ensure that the shield machine receives stable and efficient power supply. The project construction period is short and the power delivery time is tight. The State Grid Shanghai Chongming Power Supply Company, which is responsible for the implementation of the project, immediately established a special working group, carefully arranged the timetable and task book, and pressed the "fast forward" button for project implementation. Measures such as parallel process nodes and internal and external coordination were adopted to ensure that the power supply supporting projects were put into operation with high quality on schedule, laying a solid foundation for the smooth implementation of subsequent tunnel excavation operations.
Wang Yi, deputy manager of Chongtai Yangtze River Tunnel Equipment of China Railway Tunnel Bureau, said that the Chongtai Yangtze River Tunnel is currently the world-class high-speed rail cross-river tunnel project with the highest construction standards, the longest excavation distance, and the largest scale. It is an important part of the Shanghai-Nanjing-Hefei high-speed rail. . After the completion of the project, a fast new channel will be built between the Shanghai metropolitan area, Nanjing metropolitan area and Hefei metropolitan area. It will be important for optimizing the layout of the railway network along the Yangtze River, serving the coordinated development of the Yangtze River Economic Belt, and promoting high-quality integration of the Yangtze River Delta. development is of great significance. Behind all of this, it is inseparable from the stable operation and efficient cooperation of key equipment such as switch cabinets, isolating switches, vacuum circuit breakers, lightning arresters, drop-out fuses and transformers.