On June 30, the 500 kV Guanghui power transmission and transformation project, invested and constructed by the Yunnan Power Grid Company of the Southern Power Grid, was successfully completed and put into operation as the first 500 kV new energy transmission and transformation project in Yunnan Province. The core of the project includes the 500 kV Guanghui substation and its line project. Among them, two 1000 MVA main transformers were built in the substation in this phase, equipped with advanced disconnectors and vacuum circuit breakers to ensure the safety and efficiency of power transmission. In addition, there is one 500 kV outgoing line and six 220 kV outgoing lines, all equipped with drop-out fuses as overcurrent protection, further improving the stability of the power grid.
The substation is located in Yongren County, Chuxiong Yi Autonomous Prefecture. It is not only the first "million-kilowatt-level" new energy transmission substation in Yunnan Province, but also the first "gigawatt-level" 500 kV photovoltaic converging station of China Southern Power Grid. Its internal key equipment includes transformers, lightning arresters, etc., which jointly ensure the efficient operation of the substation and mainly undertake the centralized new energy grid-connected transmission task of the three counties of Yongren, Yuanmou and Dayao in Chuxiong Prefecture.
According to long-term planning, after all four main transformers in the 500 kV Guanghui substation are completed and put into use, it is expected that the installed capacity of new energy connected to the substation will reach 4 million kilowatts, which greatly promotes the grid-connected utilization of new energy.
More strikingly, the project also marks the birth of Yunnan Province's first large-scale "new energy cluster + independent energy storage" demonstration project. As an important supporting facility for the substation, the Yongren County Independent Energy Storage Demonstration Project will be built simultaneously. It contains key equipment such as transformers and energy storage devices. The annual average discharge is expected to reach 180,000 MWh, providing capacity leasing services for new energy projects and effectively coping with the intermittent problem of new energy output, thereby playing an indispensable role in improving the flexibility of the power system and ensuring the safety and stability of the power grid.
During the construction of the project, a number of technologies were innovatively used, such as digital infrastructure benchmark management and "photovoltaic storage coexistence" collaborative optimization control, to achieve the successful implementation of multiple innovative demonstration projects. With the full commissioning of the project, 24 new energy sites such as Chuxiong Yilian Photovoltaic and Wumao Photovoltaic, as well as Yongren County's 300 MW/600 MWh independent energy storage power station will be connected to the grid one after another, injecting strong momentum into energy supply and promoting green and low-carbon development.