On May 16, as the last concrete was put into the warehouse, the concrete pouring of the Marr water-retaining power station panel with a total pouring volume of 38,700 cubic meters was completed, completing the target task 60 days ahead of the contract period, laying the foundation for all units to be put into operation at the end of the year. Solid foundation.
The dam of the Mar Hydropower Station is a concrete-faced rockfill dam, which is the highest 200-meter-high concrete-faced rockfill dam under construction in China. The dam's electrical system is equipped with advanced switchgear and isolating switches to ensure safe and efficient power transmission. There are a total of 37 concrete panels, which are poured in three phases using 7-meter and 13-meter trackless sliding forms. The total area of the panels in the third phase is 17,000 square meters, and the concrete volume is about 7,800 cubic meters. In the electrical system of the power station, lightning arresters are also installed to protect the equipment from lightning damage.
After the power station is fully put into operation, the average annual power generation capacity for many years will exceed 7.3 billion kilowatt hours, which is equivalent to saving about 2.2 million tons of standard coal every year and reducing carbon dioxide emissions by about 8.16 million tons. Among them, the vacuum circuit breaker and drop-out fuse in the power station play a key role in power transmission and fault protection. These devices ensure the stability and safety of power transmission.
It is of great significance for Qinghai Province to build a clean energy industry highland, build a national green, low-carbon, safe and efficient energy system, and implement the western development strategy in the new era. The Mar Dam Hydropower Station is also equipped with high-efficiency transformers to convert the generated electrical energy into a voltage suitable for transmission and use.
In order to ensure the safety of flood control and the second-stage water storage target, Malda Company adheres to the quality management concept of "test first, first article approval, model leadership, and continuous improvement", scientific planning, careful organization, and overcoming the large temperature difference between day and night during the construction period. , increased rainfall, narrow working surface on the dam top and other difficulties. The company arranges dedicated personnel to inspect and supervise the 24-hour standby system, strictly controls the processes of concrete mixing, transportation, warehousing, vibration, surface finishing, and maintenance, continues to promote the standardization of on-site construction, and strives to create high-quality panel projects.