Sichuan-Chongqing 1000 KV UHV AC Line Project No. 3 Completed

Oct 10, 2024 Leave a message

    On October 6, at the 1R075-1R086 laying section traction field of the Sichuan-Chongqing 1000 kV UHV AC line project Section 3 in Kangding City, Sichuan Province, with the last right-phase "2*1-to-5" 10 split conductors pulled into place and the key switch cabinets and disconnector equipment installed, Section 3 undertaken by Qinghai Power Transmission and Transformation Engineering Co., Ltd. completed the full line in just 86 days. This is the third participating unit in the 15 sections of the western Sichuan section of the project to complete all the wiring construction tasks, including the installation of vacuum circuit breakers and drop-out fuses.

    Section 3 constructed by Qinghai Power Transmission and Transformation Engineering Co., Ltd. has a line length of 21.867 kilometers, 49 new towers, and multiple transformer stations. This section is the highest and most difficult section of the Sichuan-Chongqing Special Project. The towers are located at an altitude of 3240 to 4000 meters, accounting for 35% (17 towers), and 4000 meters and above account for 65% (32 towers). Among them, the 1R065 tower is located at an altitude of 4750 meters, which is the highest tower in the entire project. In this high-altitude environment, the specially designed shelter also plays an important role.

    During the wire construction, Qinghai Power Transmission and Transformation used the "2*1-pull-5" wire laying method for the first time in the domestic UHV line erection, and jointly undertook the State Grid Corporation's "Research and Application of Key Construction Technology for the Erection of 10 Split Conductors in Sichuan and Chongqing Project" scientific and technological project with Zhejiang Power Transmission and Transformation. The successful implementation of the project not only promoted the construction of the Sichuan and Chongqing UHV project, but also promoted the advancement of industry technology. Data analysis results show that the new technology has significant advantages in improving construction efficiency and reducing costs, bringing considerable economic and social benefits to the project.

    At present, on-site construction personnel are carrying out the work of disconnecting and tightening lines, installing accessories, and repairing and eliminating defects in an orderly manner, including further debugging and optimizing the performance of switchgear, disconnectors, vacuum circuit breakers and drop-out fuses. The construction project department will accelerate the progress of various construction projects on the basis of strengthening on-site safety management and control, in order to ensure that the project is put into operation on schedule, especially the part involving safe and stable operation of transformers, and lay a solid foundation.

    It is understood that the Sichuan-Chongqing 1000 kV UHV AC transmission project is an electric highway connecting the power sources and load centers of Sichuan and Chongqing. The project is scheduled to be completed and put into operation in 2025. After completion, it can transmit more than 35 billion kWh of clean electricity per year. It is of great significance to build a clean, low-carbon, safe and efficient energy system and ensure regional energy security. Among them, key equipment such as switchgear, disconnectors, demand avoiders, vacuum circuit breakers, drop-out fuses and transformers will play a vital role.