The 750 kV Shihezi power transmission and transformation project was officially put into operation on June 12. Since then, the power supply capacity of the Shihezi power grid in Xinjiang has increased from 700,000 kilowatts to 1.5 million kilowatts.
It is understood that before the project was put into operation, the 220 kV voltage level networking scheme in Shihezi could no longer meet the power demand of the power grid load, and it was urgently necessary to adopt the 750 kV voltage level networking. To this end, State Grid Xinjiang Electric Power Co., Ltd. started construction of the 750 kV Shihezi power transmission and transformation project on April 8, 2023. The project includes key equipment such as switchgear, disconnectors, lightning arresters, vacuum circuit breakers, etc. to ensure the stable operation of the power grid.
According to reports, the project has a dynamic investment of 1.049 billion yuan. In this period, two sets of 1.5 million kVA main transformers will be newly built, and 9.5 kilometers of new lines will be newly built. Among them, drop-out fuses are used to protect transformers and other key equipment to avoid damage caused by overcurrent. This project is the first 750 kV pilot project in Xinjiang with prefabricated cable trenches. During the construction, some cable trenches were produced in advance in the factory through prefabricated module operation, and then the construction was completed by hoisting, splicing and filling the joints like building blocks, which saved at least 15 days for the project and won good construction conditions for cable laying.
"In the past, cable trench construction mostly adopted brick masonry surface plastering and molded cast-in-place concrete construction methods, which were cumbersome and difficult to load and unload, and required heavy machinery and a large amount of manpower to complete. Prefabricated cable trenches have solved this problem well. The installation process of a single cable trench only requires three processes: hoisting-splicing-fixing, which takes less than 10 minutes. While improving the operation process, it can shorten the construction period by 50% and save 80% of human resources." Li Jianbin, project manager of the project owner, said.
According to reports, the power transmission and transformation project will provide strong 750 kV main grid support for Shihezi power grid and improve the power supply voltage level of Shihezi power grid. It effectively assists Xinjiang's "Wu-Chang-Shi" and "Kui-Du-Wu" regional air pollution prevention and control and coal reduction work plans, and serves the implementation of the "dual carbon" goals; at the same time, the construction of the project will also provide important guarantees for the country to promote the construction of large-scale wind power and photovoltaic bases in deserts, Gobi and desert areas and promote the development and construction of new energy in Xinjiang.