Drop-out fuse operating sequence

Mar 08, 2024 Leave a message

Operation sequence of drop-out fuse during power outage:

 

1. When the drop-out fuses are arranged horizontally and there is wind, the power outage operation should be carried out against the wind. First open the leeward side phase fall fuse, then pull the middle phase fall fuse, and finally pull the E phoenix side phase fall fuse. When the drop fuses are arranged horizontally and there is no wind, the power outage operation should first pull the middle phase drop fuse, and then pull the left and right phase drop fuses.
2. When there is wind in the triangular arrangement of the falling fuse, the power outage operation should first open the downwind side phase falling fuse, then open the upwind side phase falling fuse, and finally open the middle phase falling fuse. When there is no wind in the triangular arrangement of the fall fuses, the power outage operation should first open the fall fuses on the left and right sides, and then open the middle phase fall fuse.

 

The power supply operation sequence of drop-out fuses: Whether the drop-out fuses are arranged in a triangle or horizontally, the power supply operation must first close the middle-phase drop-out fuse, and then close the drop-out fuses on both sides.

Send Inquiry